Sagunto jetty – removal of jetty infrastructure

The Sagunto jetty, more than 1100m in length, was built in the mid 70’s by the Mining Company of Sierra Menera and continued to operate as a dock for vessels until 2009. In 2022, after years of deterioration while idle, the Valencia Port Authority deemed it unsafe and put out an emergency bid to have the jetty removed. Sacyr S.A. Construction Company won the bid and called on the Conquest MB1 to team up and tackle the job.

For the project, Conquest utilized our 1400t Main Crane and 500t Liebherr deck crane to remove several hoppers, chutes, and bridges, assist in the dismantling and eventually removing many pieces of concrete with weights up to 370t! All pieces were landed on the barge and then shifted into port to be offloaded for disposal.

CLient

Project specifications

Client

Sacyr S.A.

Location

Sagunto, Spain

Duration

3 months

Weights

Up to 370t

Scope

Dismantling assistance & removal of jetty

Location

39°39'01.7"N | 0°12'06.1"W