Dry dock refloating

In July 2019, the Conquest MB1 was contracted to refloat a 982 feet (300m) long by 228 feet (70m) wide 25,000t dry dock that had suffered irreversible structural failure and flooding during the docking of a large cruise ship. The engineering team of Resolve Marine formulated a plan to safely refloat the dry dock in two sections. Over the next three months, the drydock was successfully cut into two sections during a guillotine and the Conquest MB1.

CLient

No client logo found.

Project specifications

Client

Resolve Marine Group

Location

Grand Bahama

Duration

50 days

Weights

Up to 650t

Scope

Refloating dry dock

Location

26°31'37.13"N | 78°45'29,66"E