In July 2019, the Conquest MB1 was contracted to refloat a 982 feet (300m) long by 228 feet (70m) wide 25,000t dry dock that had suffered irreversible structural failure and flooding during the docking of a large cruise ship. The engineering team of Resolve Marine formulated a plan to safely refloat the dry dock in two sections. Over the next three months, the drydock was successfully cut into two sections during a guillotine and the Conquest MB1.
Dry dock refloating
CLient
No client logo found.
Project specifications
Client
Resolve Marine Group
Location
Grand Bahama
Duration
50 days
Weights
Up to 650t
Scope
Refloating dry dock
Location
26°31'37.13"N | 78°45'29,66"E